EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Intersection Construction
Phase: PD&E
Limits: The intersection itself and immediate surrounding area
Length: 1 miles
County:
Road:
Start of Current Phase: Mid 2019
Est. Completion of Current Phase: Mid 2025
About

On July 25, 2025, the Florida Department of Transportation (FDOT) Office of Environmental Management (OEM), pursuant to 23 U.S.C. § 327 and a Memorandum of Understanding dated May 26, 2022, and executed by the Federal Highway Administration and FDOT, granted Location and Design Concept Acceptance for the US 41 (SR 45) at Bonita Beach Road Project Development & Environment (PD&E) Study in Lee County.

The proposed improvements consist of modifying the US 41 and Bonita Beach Road signalized intersection to a partial displaced left turn (DLT) configuration, with the northbound and southbound left turn movements crossing over to the outside of opposing traffic. This design allows the northbound and southbound left turns to operate simultaneously with the through movements on US 41, improving traffic flow and reducing delays.

As part of the intersection improvement, a new northeast quadrant roadway will connect US 41 to Arroyal Road, providing additional access and circulation benefits. Multimodal features are also included, with a 12-foot shared use path provided throughout the intersection area to enhance pedestrian and bicycle connectivity.

Approval of the recommended alternative followed a comprehensive PD&E study process that evaluated multiple alternatives, including an overpass option and a no-build alternative. The study included detailed engineering and environmental analysis, interagency coordination, and robust public involvement.

This project will now proceed into the next phase of development, which is design.

 

Public Involvement

Location Design Concept Acceptance has been granted for this project, and the project will now proceed to the next phase of development, which is design. 

FDOT held a public hearing, both live online and in-person, on March 26, 2024. Materials were also available for review and comment below from March 4, 2024, and comments for the workshop were accepted in multiple ways through April 5, 2024. If you were unable to attend the hearing, the presentation recording and a summary of the public hearing are available on the website in the Project Documents section below. 

FDOT held a public workshop, with a live online event on April 3, 2023 and a live in person event on April 4, 2023. Materials were also available for review and comment below from March 27, 2023. And comments for the workshop were accepted in multiple ways through April 14, 2023. To view what was presented at the workshop, see the Project Documents section below.

View Factsheet
Contact Information
PD&E Project Manager
Patrick Bateman, PE
863-519-2792
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
Project Documents
1. Project Documents
2. Public Hearing
3. Alternatives Public Workshop
4. Project Kickoff
Project Videos
Project Images
US 41 & Bonita Beach Road Schedule - 2025