SR 777 River Road from I-75 to US 41: Construction project: Road base installation continues on the southbound roadway from south of West Villages Parkway to US 41. Road base installation, drainage installations, and curb placement continue on the future northbound roadway from the Bridge Church entrance to Aucilla Drive. Sod installation, signal, ITS, and lighting work is ongoing. Base and curb installation will begin on Center Road within the project limits. Motorists can expect single-lane closures during the day on Center Road approaching River Road. Trucks will be crossing the road at various locations using intermittent flagging operations. Pothole maintenance will continue as necessary on all current travel ways through the project.