SR 70 from Lorraine Road to Bourneside Boulevard, Bradenton: Construction project: This project includes widening SR 70 from Lorraine Road to Bourneside Boulevard from a two-lane undivided roadway to a four-lane or six-lane divided roadway, depending on the location, construction of roundabouts on SR 70 at Uihlein Road, Del Webb Boulevard, and Bourneside Boulevard, intersection improvements at the existing signalized intersection of Greenbrook Boulevard and Lorraine Road, construction of four bridges over two Braden River crossing locations, new drainage system, construction of 10-foot shared use paths, street lighting, and landscaping, and installation of new fiber optic cable connecting the two signalized intersections to Manatee County’s regional Advanced Traffic Management System (ATMS).
This week’s work will consist of:
- Crews will grade base between Arbor Green Trail and Greenbrook Boulevard.
· Excavation of the pond on the north side of SR 70 West of Uihlein Road.
- Embankment hauling and grading will occur between Bourneside Boulevard and Polo Run on the north side of SR 70. Trucks will be crossing current SR 70 travel lanes. Please be aware of flaggers stopping traffic for this crossing.
- Setting auger cast piles east of Bourneside Boulevard on the south side of SR 70.
- Driving bridge pile for the western most westbound bridge.
- Crews will grade stabilization between Bourneside Boulevard and Polo Run on the north side of SR 70.
- Installing drainage on the north side of SR 70 between Bourneside Boulevard and Polo Run
Please use caution and watch for trucks and construction vehicles entering or exiting the work zone throughout the construction limits. Work will occur Monday through Saturday from 7 a.m. to 5 p.m. Please use caution and be aware of workers and flaggers in the area.
Uihlein Road is closed to construct the north portion of the Uihlein Road roundabout. During this time no traffic will be permitted on Uihlein Road between SR 70 and Sapphire Point Drive in either direction. A complete detour and message boards are provided for the detour.
-
SR 55 (US 19) and SR 684; from 23rd Avenue W. to 39th Street E., from Terra Ceia Road to I-275 and at Royal Palm Drive, Manatee: Construction project: These projects include making improvements along State Road 55 (US 19) from 23rd Avenue W to 39th Street E, SR 55 (US 19) from Terra Ceia Rd to I-275 (NB Ramp) and along SR 684 at Royal Palm Drive in Manatee County. Improvements will involve milling and resurfacing SR 55 from 23rd Ave W to 39th St E, implementing safety improvements, guardrail replacements, sidewalk repair, lighting updates, pedestrian signal replacements, and median modifications.
- Crews will be removing and replacing sidewalk between 17th Avenue W. and Manatee Avenue E. This will require outside lane closures, and sidewalk detours along SR 55 (US 301) (US 41).
- Work will take place overnight, Sunday through Thursday, from 8 p.m. to 6:00 a.m.
- Motorists should anticipate outside or inside lane closures on SR 55 (US 301) (US 41) alternating between southbound and northbound directions. Please use caution and watch for construction vehicles entering and exiting the work zone.
- SR 684 (Cortez Road) between 103rd Street Court W. and 99th Street W. – Daily sidewalk closures for the next two weeks to facilitate directional bores. This work will be performed during the daytime, starting Monday, October 6, 2025, and will continue throughout the week. No lane closures required; however, we will need to detour pedestrian traffic.
The estimated completion date for construction is Spring 2027.