Project Details
Work Type: Widening
Phase: Construction
Limits: from US 41 to I-75
Length: 5 miles
County:
Road:
Construction Cost: $47.5 million
Start of Current Phase: Early 2022
Est. Completion of Current Phase: Early 2027
About

The Florida Department of Transportation (FDOT) District One is conducting a Design-Build project to widen River Road (SR 777) from north of US 41 to south of I-75. The project limits fall within Sarasota County. FDOT determined that widening SR 777 from two lanes to six lanes from north of US 41 to south of I-75 will meet travel demand and enhance safety along this section. The project length is approximately 5.06 miles.

In addition to building a new six-lane roadway, the contractor is constructing drainage and safety improvements, shared-use paths, wildlife crossings, signing and pavement markings, lighting, signalization, and Intelligent Transportation System (ITS) features with raised medians and intersection improvements.

Project Schedule

PD&E Study and Roadway Design: Mid-2021 to Early 2022
Public Meeting: Early 2022
PD&E Study and Roadway Design (two additional lanes from Center Road to I-75): 2024
Public Meeting: Late 2024
Construction: Early 2022 to Early 2027

Public Involvement

The Florida Department of Transportation District One held a public meeting on January 27, 2022 to share information about a design-build project to widen River Road (SR 777) from north of US 41 to just south of I-75 in Sarasota County. The design included widening the road to four lanes from I-75 to Center Rd., and six-lanes from Center Road to US 41.

In November 2024, a public meeting was held to share information about the Department’s decision to add two more lanes (one in each direction) from Center Road to I-75. More information on the reevaluation and public hearing held on November 21, 2024 can be found here.  With this decision, River Road is now being constructed as a six-lane roadway from US 41 to I-75.  

View Factsheet
Contact Information
Communications Team
Communications Office
FDOT-D1Comm@dot.state.fl.us
Communications Team
Nancy Morgan
RiverRdinfo@qcausa.com
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • SR 777 River Road from I-75 to US 41: Construction project: Road embankment installation continues on the northbound roadway from Aucilla Drive to U.S. 41. As embankment is completed, drainage installations, subgrade mixing, curb placement, and roadway grading will continue. Sod installation, signal, ITS, and lighting work are ongoing. Trucks will be crossing the road at various locations using intermittent flagging operations. Pothole maintenance will continue as necessary on all current travel ways through the project.

    NEW TRAFFIC PATTERN:

    New traffic pattern: all northbound and southbound traffic on S.R. 777 (River Road) was switched to the new southbound alignment temporarily, from just south of I-75 to Venice Avenue. Please watch for signs directing traffic. Travelers should use caution when exiting neighborhoods onto River Road and are encouraged to slow down and use caution while traveling through the work zone.