442765-1 US 27 (SR 25) from South of Tower Street to North of Tower Street
Latest NewsProject Details
| Work Type: | Intersection Construction |
|---|---|
| Phase: | Construction |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $10 million |
| Start of Current Phase: | Late 2024 |
| Est. Completion of Current Phase: | Mid 2026 |
About
US 27 (SR 25) FROM S OF TOWER ST TO N OF TOWER ST - Rigid Pavement (Concrete)
INTERSECTION Reconstruction (Project length - 0.300 miles) Goes with
US 27 (SR 25) FROM SHORELINE DR TO DAVIS & GAINES RD - Milling and resurfacing, sidewalk,
widening, drainage improvements, signalization, guardrail, signing and pavement marking, lighting, and landscaping. Project length - 6.443 miles
Public Involvement
Aika Ranieri
Community Outreach
Florida Department of Transportation
Heartland Operations Center
PH: 863-471-4881
Ai.Ranieri@dot.state.fl.us
Or
Nancy Morgan
Community Outreach
Florida Department of Transportation
Heartland Operations Center
Cell or Text: 941-720-6335
Contact Information
| Communications Team |
|---|
|
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
|
| Communications Team |
|
Aika Ranieri
(863) 464-0743
ai.ranieri@dot.state.fl.us
|
| For Media Inquiries Only |
|
fdot-d1comm@dot.state.fl.us
|