446207-1 SR 25 (US 27) from Shoreline Drive to Davis & Gaines Road
Roadwatch UpdateProject Details
Work Type: | Milling and Resurfacing |
---|---|
Phase: | Construction |
Limits: | from Shoreline Drive to Davis & Gaines Road |
Length: | 6.443 miles |
City: | |
County: | |
Road: | |
Construction Cost: | $17,162,200 |
Start of Current Phase: | Mid 2021 |
About
The Florida Department of Transportation (FDOT), District One, welcomes you to the Public Meeting
for the State Road (SR) 25 (US 27) from Shoreline Drive to Davis & Gaines Road project. FDOT is
hosting this Public Meeting to provide you with the opportunity to express your views about the
proposed improvements. Scan the QR code to visit the project website for additional details.
The objective of the project is to extend the service life of the existing pavement and improve safety on SR 25 (US 27) from
Shoreline Drive to Davis & Gaines Road. The improvements include:
• Milling and resurfacing the existing pavement. Inside paved shoulders will be
added in the medians.
• A separate design project for the Tower Street intersection will be constructed
with this project. The intersection will be fully reconstructed with concrete
pavement.
• Bicycle keyhole lanes will be constructed at the right turn lanes.
• Proposed sidewalk improvements to increase pedestrian connectivity.
• Proposed guardrail and traffic signal replacement to meet current standards.
• Modify median openings to improve safety and meet current requirements.
Three full median openings will be converted to directional openings and two
openings will be closed.
o Proposed directional median openings at CR 29, S. Main Ave., and
Heartland Blvd.
o Proposed median closures at Old SR 8, and South of Lake McCoy (no
side street).
Public Involvement
Aika Ranieri
Community Outreach Specialist
Florida Department of Transportation
Heartland Operations Center
PH: 863-471-4881 / 863-464-0743
Ai.Ranieri@dot.state.fl.us
OR
Nancy Morgan
Community Outreach
nancy.morgan@dot.state.fl.us
941.720.6335
Contact Information
Design Project Manager |
---|
Jennifer Freeman
863-519-2543
|
Communications Team |
Aika Ranieri
(863) 464-0743
ai.ranieri@dot.state.fl.us
|
For Media Inquiries Only |
fdot-d1comm@dot.state.fl.us
|
RoadWatch
-
SR 25 (US 27) from Shoreline Drive to Davis and Gaines Road and SR 25 (US 27) from North of Tower Street to South of Tower Street: Construction project: Crews are reconstructing rigid pavement on SR 25 (US 27) from north of Tower Street to south of Tower Street. Additionally, milling and resurfacing work is ongoing on US 27 from Shoreline Drive to Davis and Gaines Road.
- Caution: New Traffic Pattern. Traffic has been shifted into Phase III to reopen the southbound lanes. Motorists should expect daytime and nighttime lane closures on both northbound and southbound lanes throughout the project limits.
- Nighttime lane closure on US 27 and Interlake Boulevard / CR 621 intersection to construct a new signalized intersection.
- Southbound outside lane closures are in place between E Royal Palm Street and Shoreline Drive.
- Median Access will be permanently closed at S Main Ave and McCoy Drive the week of September 29th.
- Periodic Nighttime Lane Closure on US 27 northbound between Shoreline Drive and north of Davis & Gaines Road.
- Motorists should anticipate an inside lane closure northbound and southbound between Shoreline Drive and Interlake Boulevard for median widening.
- Shoulder closures are ongoing in both directions between Shoreline Drive and south of Interlake Boulevard, and from Lake Clay Drive South to Tomoka Boulevard North, for the lighting scope of work.
- Motorists should use caution in the area and watch for workers and equipment in the construction zone.
Anticipated completion is late 2026.