444807-1 US 41 Business (9th Street West) from 6th Avenue to Manatee Avenue
Roadwatch UpdateProject Details
Work Type: | Milling and Resurfacing |
---|---|
Phase: | Construction |
Limits: | US 41 (Tamiami Trail), from 6th Avenue to Manatee Avenue |
Length: | 0.07 miles |
Construction Cost: | $1.3 |
Start of Current Phase: | Late 2024 |
Est. Completion of Current Phase: | Mid 2025 |
About
The Florida Department of Transportation (FDOT) will begin improvements to US 41 Business (9th Street West)
from 6th Avenue West to Manatee Avenue West in Manatee County on December 16, 2024. The improvements
consist of milling and resurfacing, drainage upgrades, modified left turn lanes, signalization, lighting, and signing
and pavement markings. Single-lane closures will occur throughout the project through completion. The project
limits cover approximately 0.07 miles and the estimated project cost is $1.3 million.
FAQs
Project Improvements
- Milling and resurfacing
- Signalization and lighting
- Drainage upgrades
- Signing and pavement markings
Schedule
- Project begins December 16, 2024; estimated
- completion is mid-2025
- Be aware of changing traffic patterns with single-lane
- closures after 7 p.m.
- Follow posted speed limits during construction
Contact Information
Communications Team |
---|
FDOT-D1COMM
|
Communications Team |
Barbara Catlin
941-302-5048
barbara.catlin@dot.state.fl.us
|
Communications Team |
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
|
For Media Inquiries Only |
fdot-d1comm@dot.state.fl.us
|
RoadWatch
-
US 41 Business (9th Street West) from 6th Avenue to Manatee Avenue/SR 64: Construction project: The improvements consist of milling and resurfacing, drainage upgrades, modification and removal of a left turn lane, signalization, lighting, and signing and pavement markings. Single-lane closures will occur throughout the project through completion.
- Please be alert for intermittent lane closures overnight as the contractor performs drainage improvements, signal, lighting, and resurfacing operations.
- Median work on US 41 Business northbound from 6th Avenue West to Manatee Avenue/SR 64 will continue with intermittent lane closures from 7 p.m. to 6 a.m. throughout the project. Please use caution or plan to use an alternate route.
New traffic pattern
- On Friday, May 2, weather permitting, the left-hand turn lane going northbound on US 41 Business from 6th Avenue West to Manatee Avenue/SR 64 westbound will be permanently closed. As an alternate route, motorists wanting to go westbound on Manatee Avenue/SR 64 can turn left on 8th Avenue West and turn right onto 10th Street West northbound and then make a left onto Manatee Avenue/SR 64.
- Project completion is expected mid-2025.